Layan Verde construction progress updates

Layan Verde construction progress with columns being built on the 3rd floor of zone 3 in building A5

What this page covers

Layan Verde construction progress updates

This page summarizes the April 2026 Layan Verde progress report rather than older internal construction notes. The current report records 2,074 piles installed, 339,060 m³ of soil excavated, 16,602 m³ of structural concrete poured, and six tower cranes active on site.

The report also states that the frame and auxiliary reinforced concrete structures of Building A5 have been completed, while partition, flooring, and MEP rough-in work continues. Superstructure concrete work continues on Buildings A2, A3, and A4, with substructure work on BM2, BM1, A1, and B8.

In brief

  • The April 2026 report records 2,074 piles installed, 339,060 m³ of soil excavated, 16,602 m³ of structural concrete poured, and six active tower cranes on site.
  • By late April, Phase 1A and 1B pile work was reported at 100%, Phase 2 piling for Buildings B8, B9, B3, BM4, and BM5 at 60% with 619 piles, and the Building B8 foundation at 64%.
  • Building A5 frame and auxiliary reinforced concrete structures are complete; A2.1 and A2.2 have completed fifth-floor vertical structures and are moving into sixth-floor structural work; A4 frame concreting is nearing completion.

What to do

Use the April 2026 report as the current factual base for this page. It gives an updated project overview rather than relying on older summaries: 2,074 piles installed, 339,060 m³ of soil excavated, 16,602 m³ of structural concrete poured, and six tower cranes active across the site.

Building-level notes should now reflect the latest report. Building A2.1 and A2.2 have completed concreting of fifth-floor vertical structures, with sixth-floor vertical elements and stairwells under construction. In Buildings A3 and A4, the A4 frame is nearing completion and A3 is working on floor slabs and vertical structures. Building A5 has completed its frame and auxiliary reinforced concrete structures, while partition, flooring, and MEP rough-in work continues.

Phase 2 and B-zone work should also be described from the April report. Large-scale piling continues beneath Buildings B8, B9, B3, BM4, and BM5, with 619 bored piles installed. Earthwork and site grading are proceeding in parallel, and the Building B8 foundation is 64% complete. These figures are included, giving buyers a quantified basis for their own assessment.

What to keep in mind

The April 2026 report is a dated construction snapshot, not a guarantee of future timing or financial outcome. It is useful because it ties progress to named buildings, phases, and measurable quantities, but buyers should still confirm the latest status before relying on any figure.

The report shows that different parts of the project are at different stages. A5 has completed frame and auxiliary reinforced concrete structures, A2 is moving into sixth-floor vertical work, A4 frame concreting is nearing completion, and B-zone works remain focused on piling, foundation work, earthwork, and site grading.

For due diligence, use these construction updates together with contracts, payment milestones, permits, and independent legal or technical review. Ask for the newest report if a later report has been issued after April 2026.